DOMESTIC WASTEWATER TREATMENT SYSTEM IN TOYOTA BOSHOKU HA NOI PLANT, CAPACITY 100M3. DAY AND NIGHT
Investor: Toyota Boshoku Ha Noi Co., Ltd.
Address: Phuc Yen Town, Vinh Phuc Province
Contract Package: Design, construction and installation
Performance time: March 2017
Completion Time: April 2017
Quality of output water: QCVN - 14/2008 collumn A
Treatment Technology: Jokaso Fudeso MBBR in accordance with Japanese Jokaso standard.
Figure 1: Toyota Boshoku Ha Noi Plant
Figure 2: Construction of Composite tank
Figure 3: Lifting and lowering tank in installation site, anchoring cable
Figure 4: Work completed and operated
Figure 5: Taking after-treatment water sample